Dell, Jera, and UK-based Rhaelm partner to build a $15B, 400MW off-grid AI data center and gas power plant near Tokyo, set to begin operations around 2028 (Financial Times)

Techmeme ·
The plan pairs a 400MW private power supply with AI compute capacity outside Tokyo.

Dell, Jera, and Rhaelm are partnering on a proposed $15B off-grid AI data center and gas power plant. The project is planned near Tokyo and is expected to start operating around 2028. The setup points to power availability as part of the build, not a separate utility-side assumption. Techmeme's note