Permit hurdles push up costs for AI data centers; Oracle pivoted from gas turbines to costlier fuel cells for its Project Jupiter in NM, costing billions more (Ann Davis Vaughan/The Information)

Techmeme ·
Oracle’s power workaround for Project Jupiter added billions to the bill.

Techmeme’s note says permit hurdles pushed Oracle away from gas turbines and toward more expensive fuel cells for its proposed $165 billion AI supercampus in New Mexico. The shift was described as an attempt to salvage the project, but at a much higher cost. The item frames the episode as a sign that building large AI data centers can mean paying more than planned when power and permitting collide. Techmeme’s note